63. If the port director/center director finds a NAFTA Certificate of Origin to be illegible, defective or incomplete, the importer must be given a period of not less than _____ to present a corrected certificate.

A. 5 working days

B. 5 calendar days

C. 10 calendar days

D. 10 working days

E. 30 calendar days

[bg_collapse view=”button-green” color=”#4a4949″ icon=”arrow” expand_text=”Show Answer and Citation” collapse_text=”Hide Answer and Citation” ]

The Answer is: A

Citation: 19 CFR 181.22 (c)