2023 October No.52 – Valuation, Appraisement and Duty Assessment


Within how many days must an importer respond in writing to the Center director, if the importer disagrees with the Center director’s written notification of a proposed rate advance and increased duties?

A) Five (5) days

B) Seven (7) days

C) Ten (10) days

D) Twenty (20) days

[bg_collapse view=”button-green” color=”#4a4949″ icon=”arrow” expand_text=”Show Answer and Citation” collapse_text=”Hide Answer and Citation” ]

The Answer is: D

Citation: 19 CFR 152.104(m)