35. What is the date and time of presentation for quota priority for the following scenario? A sugar quota entry summary for Opening Moment is transmitted in the Automated Commercial Environment (ACE) and receives a pending status. The goods arrived and released February 1, the entry summary date is February 6th, and the duty payment was submitted to CBP February 8th. The sugar Opening Moment date is February 6th.
A) The date and time of presentation for quota priority is date stamped on the arrival document, February 1st.
B) The date and time of presentation is the entry summary date February 6th.
C) The date and time of presentation will be the merchandise release date, February 1st.
D) The date and time of presentation is the payment date, February 8th.
E) The date and time of presentation is 12:00 Noon (Eastern) of Opening Day.
[bg_collapse view=”button-green” color=”#4a4949″ icon=”arrow” expand_text=”Show Answer and Citation” collapse_text=”Hide Answer and Citation” ]
The Answer is: D
Citation: 19 CFR 132.13 and ACE BRPD 8.8